SSC CPO 2023 PYQ — Question 135

SSC CPO - 04 Oct 2023 - Shift 1 • Quantitative Aptitude • Q135

A and B undertake a project worth ₹36,000. A alone can do the work in 25 days. They worked together for 5 days. For the next five days, B worked alone. After that, substituted B and completed the remaining work in 5 days. The share of A in the earnings is:   

Show answer & explanation

Correct answer: A

Explanation

The correct answer is option 1 i.e. Rs. 14,400.

Given:

A and B undertake a project worth ₹36,000

A alone can do the work in 25 days

A and B worked together for 5 days and For the next five days, B worked alone. After that,
substituted B and completed the remaining work in 5 days

Concept used:

Total work = Time × Efficiency

Explanation:

According to the question

⇒ (A + B) × 5 + B × 5 + A × 5 = A × 25

⇒ 2A + 2B = 5A

⇒ 3A = 2B

⇒ A/B = 2/3

Hence, The share of A in the earnings = (2/5) × 36000 

⇒  Rs. 14400