SSC Selection Post 2025 PYQ — Question 37

SSC Selection Post - Graduation Level - 29th August 2025 - Shift 1 • Quantitative Aptitude • Q37

A and B together finish work in 10 days. B and C in 12 days. A and C in 15 days. How many days will C take to do the work alone?

Show answer & explanation

Correct answer: A

Explanation

1-day work efficiency of A + B = 1/10

1-day work efficiency of B + C = 1/12

1-day work efficiency of A + C = 1/15

Sum of the three equations,

= 1/10 + 1/12 + 1/15

= (6 + 5 + 4)/60

= 15/60

= 1/4

1-day work efficiency of A + B + C = 1/8

1-day work efficiency of C = (A + B + C) − (A + B)

= 1/8 − 1/10

= (5 − 4)/40

= 1/40

Therefore, C alone will complete the work in 40 days.