A and B together finish a job in 9 days. If A alone takes 18 days, how many days will B alone take?

Show answer & explanation

Correct answer: C

Explanation

Given:

A + B's time = 9 days

A's time = 18 days

By formula:

Work rate = 1 / time

A + B's rate = 1/9

A's rate = 1/18

B's rate = 1/9 − 1/18

= (2 − 1) / 18

= 1/18

B's time = 18 days