SSC GD 2023 PYQ — Question 50

SSC GD Constable (English) - 17 Jan 2023 - Shift 2 • Quantitative Aptitude • Q50

A and B together do a piece of work in 12 days, B and C in 15 days, and C and A in 20 days. In how many days can they finish the work if all of them work together?

Show answer & explanation

Correct answer: C

Explanation

The correct answer is Option 3 i.e. 10.

A and B together do a piece of work in 12 days, B and C in 15 days, and C and A in 20 days

L.C.M(12, 15, and 20) = 60

The efficiency of A and B = 60/12 = 5 units

The efficiency of B and C = 60/15 = 4 units

The efficiency of A and B = 60/20 = 3 units

The efficiency of all three = 2(A + B + C) = 12

(A + B + C) = 6

Time taken = 60/6 = 10 days