SSC CGL 2022 PYQ — Question 52

SSC CGL - 02 Dec 2022 - Shift 4 • Quantitative Aptitude • Q52

A and B together can do a piece of work in 50 days. If A is 40% less efficient than B, in how many days can A working alone complete 60% of the work?

Show answer & explanation

Correct answer: C

Explanation

The correct answer is option 3 i.e. 80

Given:

(A + B) can together complete the work in 50 days.

A is 40% less efficient than B

Concept Used: 

Total work = Efficiency × total time

Explanation:

Let the efficiency of B be 5x, then efficiency of A = 60% of 5x = 3x

Total efficiency of (A + B) = 8x

Total work = 8x × 50 = 400x

Amount of work A has to complete = 60% of 400x = 240x

Time taken by A alone = 240x/3x = 80

Hence, the time taken by A to complete 60% of the total work is 80 days.