A and B together can complete a work in 12 days. If A alone can complete the work in 20 days, how many days will B alone take to complete the work?

Show answer & explanation

Correct answer: B

Explanation

Given:

A + B complete the work together = 12 days

A completes the work alone = 20 days

A + B's rate = 1/12

A's rate = 1/20

B's rate = 1/12 − 1/20

= 5/60 − 3/60

= 2/60

= 1/30

B will complete the work alone = 30 days