SSC GD 2023 PYQ — Question 55

SSC GD Constable (English) - 23 Jan 2023 - Shift 4 • Quantitative Aptitude • Q55

A and B together can complete a work in 8 days. A alone can complete it in 16 days. If B works at 50 percent efficiency, then in how many days A and B together will complete the work?

Show answer & explanation

Correct answer: A

Explanation

The correct answer is Option 1 i.e. 32/3 days.

A and B together can complete a work in 8 days. A alone can complete it in 16 days

L.C.M(8 and 16) = 16

The efficiency of A and B together = 16/8 = 2 units

The efficiency of A = 16/16 = 1 unit

So, The efficiency of B = 2 - 1 = 1 unit

B works with 50% efficiency = 1/2 = 0.5 units

Time taken = 16/(0.5 + 1) = 16/1.5 = 160/15 = 32/3 days