SSC CGL 2017 PYQ — Question 16

SSC CGL Tier II Quant - 12/01/2017 • Quantitative Aptitude • Q16

A and B together can complete a piece of work in 12 days. They worked together for 5 days and then A alone finished the rest work in 14 days. A alone can complete the work in _____.

Show answer & explanation

Correct answer: A

Explanation

  The correct answer is option 1 i.e. 24 days

Understanding

Application

A and B together can complete a piece of work in 12 days.

Work done in 5 days = 5/12

So,

Remaining work = 7/12

A completes the remaining work in 14 days

So,

Required time = 14/(7/12) = 24 days