SSC CHSL 2023 PYQ — Question 65

SSC CHSL - 07 Aug 2023 - Shift 2 • Quantitative Aptitude • Q65

A and B can finish the work in 6 days and 4 days, respectively. A alone worked on it for 2 days. Thereafter, B joined him. How much total time was taken by them to finish the work?

Show answer & explanation

Correct answer: A

Explanation

The correct answer is option 1 i.e. 335\frac3{5} days.

A and B can finish the work in 6 days and 4 days, respectively.

Let the total work = 12 (LCM of 6 and 4)

Efficiency of A = 12/6 = 2

Efficiency of B = 12/4 = 3

Work done by A in 2 days = 2 × 2 = 4

Remaining work = 12 - 4 = 8

Time required for A and B to do remaining work = 8/(2 + 3) = 8/5 = 1351\frac{3}{5} days

Total time = 2 + 1351\frac{3}{5} = 3353\frac{3}{5} days

Therefore, the time required to finish the work is 3353\frac{3}{5} days.