SSC Selection Post - Higher Secondary Level 2022 - 11 Feb 2022 - Shift 1 • Quantitative Aptitude • Q67

A and B can finish a job in 10 days and 5 days, respectively. They worked together for 2 days, after which B was replaced by C, and the job was finished in the next 3 days. In how many days will C alone finish 50% of the job?

Show answer & explanation

Correct answer: A

Explanation

The correct answer is option 1 i.e. 15.

LCM(10, 5) = 10

The efficiency of A = 10/10 = 1 units

The efficiency of B = 10/5 = 2 units

Work done in 2 days = 2 × 3 = 6 units

Remaining work = 10 - 6 = 4 units

Now, A and C together finish 4 units in 3 days

A's 3 days' work = 3 units

Work done by C = 4 - 3 = 1 unit

So, the efficiency of C = 1/3 units

Time taken by C to cover 50% of the work = 5135\over{1\over3} = 15 days