SSC GD 2025 PYQ — Question 42

SSC GD Const 2025 (English) - 07 Feb 2025 - Shift 2 • Quantitative Aptitude • Q42

A and B can do a work in 30 days and 10 days, respectively. If they start the work with A and work on alternate days, in how  many days will the work  be complete?

Show answer & explanation

Correct answer: B

Explanation

The correct answer is Option 2 i.e.  151315\frac{1}{3}days .

A's 1 day work = 1/30

B's 1 day work = 1/10

2 days work = 1/30 + 1/10 = 2/15

14 days work = 7 × 2/15 = 14/15

15th day (A) = 1/30 → total = 29/30

Remaining = 1/30

16th day (B) → 1/10 per day

Time = 1/30 ÷ 1/10 = 1/3 day

= 15⅓ days