SSC Selection Post 2024 PYQ — Question 67

SSC Selection Post - Graduation Level - 20 Jun 2024 Shift 3 • Quantitative Aptitude • Q67

A and B can do a work in 15 days and 30 days, respectively. They start working together, but A leaves after 3 days. How much time will B take to complete the remaining work?

Show answer & explanation

Correct answer: B

Explanation

The correct answer is option 2 i.e. 21 days.

Let the total work to be done (LCM of 15 and 30) be 30 units.

Efficiency of A = 30/15 = 2 units/day

Efficiency of B = 30/30 = 1 unit/day

Work done by A and B together in 3 days = (2 + 1) × 3 = 9 units

Remaining work = 30 - 9 = 21 units

Time taken by B to complete remaining work = 21/1 = 21 days