SSC CGL 2024 PYQ — Question 64

SSC CGL - 19 Sep 2024 - Shift 2 • Quantitative Aptitude • Q64

A and B can do a work in 12 days and 16 days, respectively. If they work together for 6 days, then the fraction of the work left is _________.

Show answer & explanation

Correct answer: C

Explanation

The correct answer is option 3 i.e. 181\over8.

Time required for A to do the work = 12 days

So, A does 1/12 of the work in 1 day.

Time required for B to do the work = 16 days

So, B does 1/16 of the work in 1 day.

Work done by A and B together in 1 day = (1/12) + (1/16) = 7/48 of the work

Work done by A and B together in 6 days = (7/48) × 6 = 7/8 of the work

Remaining work = 1 - (7/8) = 1/8

Therefore, the fraction of the work left is 1/8.