SSC MTS 2026 PYQ — Question 5

SSC MTS - 16 Feb 2026 - Shift 2 • Quantitative Aptitude • Q5

A and B can do a piece of work in 12 days and 18 days, respectively. They work on alternate days, starting with A. How many days will it take to complete the work?

Show answer & explanation

Correct answer: B

Explanation

Given:

A = 12 days, B = 18 days

A's rate = 1/12

B's rate = 1/18

Work done in 2 days = 1/12 + 1/18 = (3 + 2)/36 = 5/36

1 cycle (2 days) = 5/36

7 cycles (14 days) ⇒ 35/36 of the work

Remaining work = 1/36

On the next day, A will work

A's work in 1 day = 1/12

Time required = (1/36) ÷ (1/12) = 1/3 day

Total time = 14 + 1/3 = 14⅓ days