A and B can complete a work together in 48 days. A is 4 times as work efficient as B In how many days can B alone complete the work?

Show answer & explanation

Correct answer: C

Explanation

The correct answer is Option 3 i.e. 240 days

Given that

A is 4 times as work-efficient as B.

A and B can complete a work together in 48 days.

B can alone complete the work in d days.

According to the question

(A +B ) × 48 = B × d

5 × 48 = 1 × d

d = 240 days