A and B can complete a work in 80 days and 96 days, respectively. They completed the work in 32 days with the help of C. How many days will C take to complete the entire work alone?
Show answer & explanation
Correct answer: C
Explanation
The correct answer is option 3 i.e. 120
No of days taken = Work/ Efficiency per day
L.C.M of 80,96,32 = 480
Efficiency of A = 480/80 = 6
Efficiency of B = 480/96 = 5
Efficiency of (A+B+C) = 480/32 = 15
Efficiency of C = (15 - 6 - 5) = 4
Work done by C = 480/4 = 120 days