SSC CGL 2021 PYQ — Question 67

SSC CGL - 16 Aug 2021 - Shift 2 • Quantitative Aptitude • Q67

A and B can complete a work in 15 days and 10 days respectively. They started doing the work together but after 4 days B had to leave. Then A working with a new worker C complete the remaining work in 3 days . If C works alone , in how many days he can do 40% of the same work ?

Show answer & explanation

Correct answer: A

Explanation

The correct answer is option 1 i.e. 9.

Given :

A and B can complete a work in 15 days and 10 days

A and B work together for 4 days

A and C complete the remaining work in 3 days

Calculations :

A and B one day work = 1/15 + 1/10 = 1/6

A and B work for 4 days = 4 × 1/6 = 2/3

Remaining work = 1 - 2/3 = 1/3

The remaining work is completed in 3 days by A and C

⇒ 1/3 × 1/3 = 1/9

Let C's one-day work be 1/C

⇒ 1/15 + 1/C = 1/9

⇒ 1/C = 2/45

C can complete the whole work in 45/2 days

Time taken by C to complete 40% of the total work

⇒ (40/100) × 45/2 = 9 days

Hence, the Time taken by C to complete 40% of the total work is 9 days.