SSC CHSL 2025 PYQ — Question 69

SSC CHSL - 26 Nov 2025 - Shift 1 • Quantitative Aptitude • Q69

A and B can complete a work in 12 days, B and C can complete the same work in 15 days. A, B, and C together can complete the work in 10 days. How long will it take for A and C together to complete the work?

Show answer & explanation

Correct answer: C

Explanation

Given:

A + B = 12 days

B + C = 15 days

A + B + C = 10 days

A + B = 1/12

B + C = 1/15

A + B + C = 1/10

(A + C) = (A + B + C) − B

Find B first

B = (A + B) + (B + C) − (A + B + C)

B = 1/12 + 1/15 − 1/10

= (5 + 4 − 6)/60

= 3/60

= 1/20

Now

A + C = 1/10 − 1/20 = 1/20

Time = 20 days

A and C together will complete the work in 20 days.