SSC Selection Post 2025 PYQ — Question 41

SSC Selection Post - Matriculation Level - 24th July 2025 - Shift 1 • Quantitative Aptitude • Q41

A and B can complete a work in 8 days. B alone can do it in 12 days. In how many days will A alone complete the work?

Show answer & explanation

Correct answer: B

Explanation

Combined 1-day work efficiency of A and B = 1/8

B's 1-day work efficiency = 1/12

Therefore, A's 1-day work efficiency = 1/8 - 1/12

= (3 - 2)/24

= 1/24

So, A alone will complete the work in = 24 days