SSC GD 2021 PYQ — Question 70

SSC GD Constable (English) - 3rd December 2021 Shift 2 • Quantitative Aptitude • Q70

A and B can complete a work in 12 days and 18 days, respectively. They worked together for 4 days, after which B was replaced by C and the remaining work was completeed by A and C in the next 4 days. In how many days will C alone can complte one third of the same work?

Show answer & explanation

Correct answer: B

Explanation

The correct answer is option 2 i.e. 12 days

Given:

A and B can complete a work in 12 days and 18 days. 

They worked together for 4 days, after which B was replaced by C.

The remaining work was completed by A and C in the next 4 days.

Concept used:

Total work = Time × Efficiency

Calculations:

Total work (LCM of 12 and 18) = 36 units

Efficiency of A = 36/12 = 3 units

Efficiency of B = 36/18 = 2 units

Total efficiency of A + B = 3 + 2 = 5 units

Work done in 4 days = 4 × 5 = 20 units

Remaining work = 36 - 20 = 16 units

Remaining work is done by (A + C) in 4 days = 16/4 = 4 units

We know, A + C = 4

Efficiency of C = 4 - 3 = 1 unit

Required time taken by C to complete one third of the total work = 36/(3 × 1) = 12 days