SSC Selection Post 2022 PYQ — Question 75

SSC Selection Post - Matriculation Level 2022 - 3 Aug 2022 - Shift 1 • Quantitative Aptitude • Q75

A and B can complete a piece of work in 12 days and 18 days, respectively. A begins to do the work and they work alternately, one at a time, for one day each. The whole work will be completed in ________.

Show answer & explanation

Correct answer: B

Explanation

The correct answer is option 2 i.e. 1413days14{1\over3}days.

A can finish the work in 12 days 

B can finish the work in 18 days 

LCM of 12 and 18 = 36

Efficiency of A = 36/12 = 3 unit per day, B = 36/18 = 2 unit per day

Their 2 days work = 3 + 2 = 5 unit

7 × 2 days = 5 × 7

14 days = 35 unit 

Remaining work done by A = (36 - 35)/3 = 1/3 days

total time = 14 + 1/3 = 141314{1\over3} days