SSC CGL 2022 PYQ — Question 54

SSC CGL - 06 Dec 2022 - Shift 3 • Quantitative Aptitude • Q54

A and B can complete a piece of work in 10 and 16 days respectively. A begins to do the work and they work alternatively one at a time for one day each. The whole work will be completed in :

Show answer & explanation

Correct answer: A

Explanation

The correct answer is option 1 i.e.  1214days12\frac{1}{4} days

Calculations:

Total work (LCM of 10 and 16) = 80 units

Efficiency of A = 80/10 = 8

Efficiency of B = 80/16 = 5

Work done in 2 days, if they work alternatively starting with A 

⇒ 2 days = 13 unit work

⇒ 12 days = 78 unit work

Remaining work is completed by A = 2/8 = 1/4

Hence total time = 12 + 1/4 = 12(1/4) days