SSC Selection Post 2024 PYQ — Question 55

SSC Selection Post - Matriculation Level - 26 June 2024 - Shift 1 • Quantitative Aptitude • Q55

A and B can complete a piece of work in 25 days and 55 days, respectively. The total number of days (in whole number) to complete the work, if A and B both work together, is:

Show answer & explanation

Correct answer: C

Explanation

The correct answer is Option 3 i.e. 18.

Work done by A in one day = 1 / 25

Work done by B in one day = 1 / 55

Work done by A and B together in one day = (1 / 25) + (1 / 55)

⇒ Work done by A and B together in one day = (1)/(25) + (1)/(55)

⇒ Work done by A and B together in one day = (55 + 25)/(25 × 55)

⇒ Work done by A and B together in one day = (80)/(1375)

⇒ Work done by A and B together in one day = (16)/(275)

Total time to complete the work = 1 / ((16)/(275))

⇒ Total time to complete the work = (275)/(16)

⇒ Total time to complete the work = 17.1875 days

Rounding to the whole number, total time = 18 days