SSC CGL 2023 PYQ — Question 63

SSC CGL - 18 July 2023 - Shift 2 • Quantitative Aptitude • Q63

A and B alone can do a piece of work in 4 and 9 days, respectively. In how many days will the work be completed, if they both work on alternate days, starting with B?

Show answer & explanation

Correct answer: B

Explanation

The correct answer is option 2 i.e. 523\frac{2}{3}.

Given:

A and B alone can do a piece of work in 4 and 9 days, respectively.

Calculations:

Total work (LCM of 4, 9) = 36 units

Efficiency of A = 36/4 = 9

Efficiency of B = 36/9 = 4

If they both work on alternate days, starting with B

In 2 days, total work completed = (4 + 9) = 13

In 5 days, total work completed = 13 × 2 + 4 = 30

The remaining work (36 - 30 = 6) will be completed in 6/9, i.e. 2/3 days

Hence, the total work completed by them in 523\frac{2}{3} days.