SSC CGL 2023 PYQ — Question 57

SSC CGL - 18 July 2023 - Shift 3 • Quantitative Aptitude • Q57

A alone can finish a work in 15 days. A works only for the first two days and the last two days. The rest work is done by B and the work is completed in 20 days. In how many days A and B together can finish the work?

Show answer & explanation

Correct answer: C

Explanation

The correct answer is Option 3 i.e. 809\frac{80}{9}.

Given:

A can complete the whole work in 15 days.

A worked for the first and last 2 days.

B worked for 16 days.

Calculations:

Let the efficiency of A and B be x and y.

⇒ (2 + 2)x + 16y = 15x

⇒ 4x + 16y = 15x

⇒ 16y = 11x

⇒ x/y = 16/11

Total work = 15x = 15 × 16 = 240

Required time taken = 240/27 = 80/9 days