A alone can do a work in 20 days, B alone in 30 days. They work together for 6 days, then A leaves. How many more days will B take to finish the remaining work?

Show answer & explanation

Correct answer: C

Explanation

Given:

A completes the work in = 20 days

B completes the work in = 30 days

Both work together for = 6 days

According to the formula:

Work done in 1 day = 1 / Total days

A's work in 1 day = 1/20

B's work in 1 day = 1/30

(A + B)'s work in 1 day

= 1/20 + 1/30

LCM = 60

= 3/60 + 2/60

= 5/60

= 1/12

Work done in 6 days = 6 × 1/12 = 1/2

Remaining work = 1 − 1/2 = 1/2

Now, B will work alone

B's work in 1 day = 1/30

Time required = (1/2) ÷ (1/30) = 15 days