A alone can complete a work in 18 days and B alone in 14 days. Starting with A, they work on alternate days. The total work will be completed in:

Show answer & explanation

Correct answer: B

Explanation

The correct answer is option 2 i.e. 15797\over9 days.

Total work = LCM of 18 and 14 = 126

Efficiency of A = 126/18 = 7

Efficiency of B = 126/14 = 9

2 days work of A and B = 7 + 9 = 16

Work done in 14 days = 16 × 7 = 112

Work done on 15th day by A = 7

Remaining work = 126 - 112 - 7 = 7

Time required for B to complete the remaining work = 7/9 days

Total time = 15 + (7/9) = 15797\over9 days