SSC GD Constable (English) - 10th December 2021 Shift 1 • Quantitative Aptitude • Q62

A alone can complete a piece of work in 18 days and B alone can complete the same work in 24 days. A and B undertook the work for Rs. 22500. They took the help of C and completed the work in 8 days. How much is to be paid to A?

Show answer & explanation

Correct answer: B

Explanation

The correct answer is option 2 i.e. Rs. 10000.

Given:

A alone can complete a piece of work in 18 days

B alone can complete the same work in 24 days

A and B undertook the work for Rs. 22500

They took the help of C and completed the work in 8 days

Concept Used:

Total work = Efficiency × Time Taken

Calculations:

Total work (LCM of 18, 24, and 8) = 72 units

Efficiency of A = 72/18 = 4 units

Efficiency of B = 72/24 = 3 units

Efficiency of (A + B + C) = 72/8 = 9 units

Amount paid to A = (22500/9) × 4 = Rs 10000