SSC MTS 2026 PYQ — Question 17

SSC MTS - 17 Feb 2026 - Shift 2 • Quantitative Aptitude • Q17

A alone can complete 25 percent part of a work in 20 days. A alone will complete 60 percent part of the same work in how many days?

Show answer & explanation

Correct answer: B

Explanation

Given:

25% of the work = 20 days

Time required for 60% of the work = 20 × (60/25)

= 20 × (12/5)

= 4 × 12

= 48 days