SSC GD 2025 PYQ — Question 51

SSC GD Const 2025 (English) - 13 Feb 2025 - Shift 2 • Quantitative Aptitude • Q51

 80 men can construct a small footpath in 100 days. How many more men should be employed if the job is to be finished in 25 days?

Show answer & explanation

Correct answer: B

Explanation

The correct answer is Option 2 i.e. 240.

Work = number of men × days

Work = 80 × 100 ⇒ 8000 man-days

Men required = Work ÷ 25 ⇒ 8000 ÷ 25 ⇒ 320

More men needed = 320 − 80 ⇒ 240