SSC CHSL 2022 PYQ — Question 64

SSC CHSL - 2 June 2022 - Shift 3 • Quantitative Aptitude • Q64

6 men or 2 women or 4 boys can finish a work in 77 days. How many days will 1 man, 1 woman and 1 boy together take to finish the same work?

Show answer & explanation

Correct answer: C

Explanation

The correct answer is Option 3 i.e. 84.

6 men or 2 women or 4 boys can finish the work in 77 days.

Total number of days × total number of workers = Total work done

ATQ -

The ratio of efficiency of men and women -

6m = 2w

m/w = 1/3

m : w = 1 : 3  .....(1

The ratio of efficiency of women and boys -

2w = 4b

w/b = 2/1

w : b = 2 : 1

Multiply the first ratio by 2 to make the ratio equal.

m : w = 2 : 6..... (3

Multiply the second ratio by 3 to make the ratio equal.

w : b = 6 : 3..... (4

By comparing eq (3 and (4 -

The ratio efficiency of m : w : b = 2 : 6 : 3

Total work done = 6(m) × 77 = 6 × (2) × 77 = 924

Total work is done by 1 man, 1 woman, 1 boy in = 924/( 2 + 6 + 3) = 84 days