40 persons can repaira bridge in 12 days. If 8 more persons join them, then in how many days bridge can be repaired?

Show answer & explanation

Correct answer: B

Explanation

The correct answer is option 2 i.e. 10 days.

Understanding/Application

We know that M1D1 = M2D2 where M and D are Number of men and Number of days respectively.

M1 = 40 

D1 = 12

M2 = 40 + 8 = 48

M1D1 = M2D2

40(12) = 48(D2)

D2 = 10 days