40 men can complete a work in 15 days. Three days after they started working, 20 more men joined them. In how many days the total work will be completed?

Show answer & explanation

Correct answer: C

Explanation

The correct answer is option 3 i.e. 11

Concept used:

Work = Number of people × number of days

Calculations:

⇒ Total work = 40 × 15 = 600 units

40 men worked for 3 days, work done = 40 × 3 = 120 units

Remaining work = 600 - 120 = 480 units

20 more men joined the work, total men = 40 + 20 = 60 

Time taken = 480/60 = 8 

Total time = 3 + 8 = 11 days