40 men can complete a work in 15 days. Five days after they started working, 10 more men joined them. In how many days will the total work be completed?

Show answer & explanation

Correct answer: A

Explanation

The correct answer is option 1 i.e. 13

 

40 men can complete a work in 15 days,

⇒Hence the total work will be done = 40 × 15

After 5 days,

⇒The work will be done = 40 × 10 

Now the work 10 more men joined,

Work done,   Men1 × Days1 = Men2 × Days2

40 × 10 = 50 × Days

⇒ Days = 8

Hence total number of days = 8 + 5 =13 days.