SSC CHSL 2025 PYQ — Question 65

SSC CHSL - 17 Nov 2025 - Shift 3 • Quantitative Aptitude • Q65

4 boys and 6 girls can complete the work in 8 days, while 3 boys and 7 girls can complete it in 10 days. In how many days will 10 girls complete it?

Show answer & explanation

Correct answer: D

Explanation

Given:

4 boys + 6 girls → 8 days

3 boys + 7 girls → 10 days

(4 boys + 6 girls) × 8 = (3 boys + 7 girls) × 10

32 boys + 48 girls = 30 boys + 70 girls

2 boys = 22 girls

1 boy = 11 girls

Total work = (3 boys + 7 girls) × 10

= {(3 × 11) + (7 × 1)} × 10

= (33 + 7) × 10

= 40 × 10

= 400

Work rate of 10 girls = 10

Time = 400 / 10 = 40 days

10 girls will complete the work in 40 days.