38 men can do a piece of work in 10 days. Find the time required by 10 men to do thrice the work.
Show answer & explanation
Correct answer: B
Explanation
Given:
38 men do 1 job in 10 days.
Work = 3 times
Men = 10
Formula:
Work = (Men × Days)
38 × 10 = 10 × T / 3
380 = 10T / 3
1140 = 10T
T = 114 days