SSC CPO 2019 PYQ — Question 125

SSC CPO Tier I - 12th March 2019 - Shift 2 • Quantitative Aptitude • Q125

36 persons working 8 hours a day can do 3 units of work in 12 days. How many persons are required to do 5 units of that work in 16 days, if they work for 6 hours a day?

Show answer & explanation

Correct answer: B

Explanation

The correct answer is Option 2 i.e. 60

We know that:

[M1 × D1 × H1]/W1 = [M2 × D2 × H2]/W2

So,

[36 × 12 × 8]/3 = [M2 × 16 × 6]/5

⇒ 144 × 5 = M2 × 12

⇒ M2 = 12 × 5 = 60 persons