SSC Selection Post 2025 PYQ — Question 48

SSC Selection Post - Higher Secondary Level - 28th July 2025 - Shift 2 • Quantitative Aptitude • Q48

36 men can complete a work in 36 days. They started working together. But 6 men kept on leaving the job every 7th day. In how many days will the work be completed?

Show answer & explanation

Correct answer: C

Explanation

Work = 36 × 36 = 1296 man-days

Work done in first 42 days:

7 × (36 + 30 + 24 + 18 + 12 + 6)
= 7 × 126
= 882 man-days

Remaining work:

1296 − 882 = 414 man-days

Remaining 6 men complete it in:

414 ÷ 6 = 69 days

Total time = 42 + 69 = 111 days

Answer: 111 days (Option 3)