SSC CGL 2025 PYQ — Question 64

SSC CGL - 22 Sep 2025 - Shift 1 • Quantitative Aptitude • Q64

35 men can do a piece of work in 8 days. Find the time required by 16 men to do four times the work.

Show answer & explanation

Correct answer: A

Explanation

The correct answer is option 1 i.e. 70 Days.

Total work = 35 × 8 = 280 man-days

Four times of work = 4 × 280 = 1120 man-days

Time required for 16 men = 1120/16 = 70 days