SSC Selection Post 2024 PYQ — Question 51

SSC Selection Post - Graduation Level - 26 June 2024 - Shift 3 • Quantitative Aptitude • Q51

30 persons working 10 hours a day can do 5 units of work in 12 days. How many people are required to do 8 units of that work in 16 days if they work for 8 hours a day?

Show answer & explanation

Correct answer: C

Explanation

The correct answer is option 3 i.e. 45.

Total work = 30 × 10 × 12 = 3600 man-hours for 5 units

So, 1 unit = 3600 ÷ 5 = 720 man-hours

Then, 8 units = 8 × 720 = 5760 man-hours

Let required persons be x:

x × 8 hours/day × 16 days = 5760

x × 128 = 5760

x = 5760 ÷ 128 = 45