SSC GD 2019 PYQ — Question 73

SSC GD Constable (English) - 3 March 2019 Shift 3 • Quantitative Aptitude • Q73

30 persons can do a piece of work in 24 days. How many more people are required to complete the work in 20 days?

Show answer & explanation

Correct answer: D

Explanation

The correct answer is option 4 i.e. 6

Total work days = 24 × 30 = 720 workdays

⇒ Number of persons required to do the work in 20 days = 720/20

⇒ 36 persons

⇒ Extra = 36 - 30 = 6 persons