30 men can complete a piece of work in 24 days. 12 days after they started working together, 10 more men joined them. How many days will they now take to complete the remaining work?

Show answer & explanation

Correct answer: D

Explanation

The correct answer is option 4 i.e. 9 days

According to the question,

Total work = 30 × 24 = 720 units

One day work of 30 men = 1/24 units

12 days work of 30 men = 12 × 1/24 = 1/2 units

12 days later 10 more men joined them,

Total no. of men  = 30 + 10 = 40 men

Half of the work is done by 30 men then remaining work = 720/2 = 360 units

Time required to complete 360 units of work by 40 men = 360/40 = 9 days