SSC GD 2023 PYQ — Question 55

SSC GD Constable (English) - 7 Feb 2023 - Shift 1 • Quantitative Aptitude • Q55

24 men complete a work in 9 days. 3 days after they started working, 8 more men joined them. How many days will all of them take to complete the remaining work?

Show answer & explanation

Correct answer: D

Explanation

The correct answer is Option 4 i.e. 4.5.

Total work = 24 × 9 = 216 days

The remaining work will be completed in x days

⇒ 24 × 3 + 32 × x = 216

⇒ 72 + 32x = 216

⇒ 32x = 216 - 72

⇒ 32x = 144

⇒ x = 144/32 = 4.5 days