24 men can complete a work in 15 days. How many men are needed to complete the same work in 10 days?

Show answer & explanation

Correct answer: C

Explanation

The correct answer is option 3 i.e. 36.

Total work = (24 × 15) = 360

Total men are needed to complete the same work in 10 days = 360/10 = 36 men