SSC GD 2023 PYQ — Question 55

SSC GD Constable (English) - 6 Feb 2023 - Shift 4 • Quantitative Aptitude • Q55

20 men can finish a piece of work in 5 days, whereas it takes 24 women to finish it in 5 days. If 30 men and 12 women undertake to complete the work, how many days will they take to complete it ?

Show answer & explanation

Correct answer: D

Explanation

The correct answer is Option 4 i.e. 2.5.

Total work = Efficiency × Time taken

Let the efficiency of 1 man and 1 woman be x and y respectively

Total work done by 20 men in 5 days = 20x × 5 = 100x

Total work done by 24 women in 5 days = 24y × 5 = 120y

According to the question

⇒ 100x = 120y

⇒ x/y = 120/100

⇒ x/y = 6/5

⇒ x : y = 6 : 5

Suppose, x = 6 and y = 5

Total work = 20 × 6 × 5 = 600 units

\Work done by 30 men and 12 women in 1 day = 30  × 6 + 12  × 5 = 180 + 60 = 240 units

15 men and 6 women, complete the whole work in = 600/240 = 2.5 days