SSC Selection Post 2022 PYQ — Question 55

SSC Selection Post - Matriculation Level - 1 Aug 2022 - Shift 1 • Quantitative Aptitude • Q55

20 men can complete the work in 10 days. Five days after they started working, 5 more men joined them. In how many days will the total work be completed?

Show answer & explanation

Correct answer: C

Explanation

The correct answer is option 3 i.e. 9.

Total work = 20 × 10 = 200 units

Work in first 5 days = 20 × 5 = 100 units

Remaining work = 200 − 100 = 100 units

Now, number of men = 20 + 5 = 25

Remaining days = 10025100\over25 = 4

Total time = 5 + 4 = 9 days