18 men can complete a work in 20 days. After 10 days, 6 men leave. In how many more days will the remaining men finish the work?

Show answer & explanation

Correct answer: D

Explanation

Given:

18 men → 20 days

6 men leave after 10 days

Total work = 18 × 20 = 360

Work done in 10 days = 18 × 10 = 180

Remaining work = 360 − 180 = 180

Now remaining men = 18 − 6 = 12

Time to complete the remaining work = 180 / 12 = 15 days