18 men can complete of a work in 10 days. How many people are required to complete of the same work in 5 days?
Show answer & explanation
Correct answer: C
Explanation
The correct answer is option 3 i.e. 72.
18 men can complete of a work = 10 days
18 men can complete a work = 10 × 5 days = 50 days
Let's assume x men of the same work = 5 days
So, x men complete the same work = × 5 = 25/2 days
So,
According to the question,
men × days = men × days
⇒ 18 × 50 = x × 25/2
x = 72 men