SSC CGL 2023 PYQ — Question 68

SSC CGL - 17 July 2023 - Shift 2 • Quantitative Aptitude • Q68

15 men can complete a work in 25 days, and 25 women can complete the same work in 40 days. If all 15 men and 25 women work together, in how many days will the work be completed?

Show answer & explanation

Correct answer: A

Explanation

The correct answer is option 1 i.e. 15513\frac{5}{13} days

Given that

15 men can complete a work in 25 days

25 women can complete the same work in 40 days

Let the efficiency of a men be M and a woman be W

According to the question

⇒ 15 M × 25 = 25 W × 40

⇒ M/W = 8/3

Total work = 15 M × 25 = 15 × 8 × 25 = 3000

Hence, all 15 men and 25 women work together,

⇒ 3000/(15 × 8 +  25 × 3) = 3000/195 = 15513\frac{5}{13} days