12 men can complete a work in 10 days. How many more men are required to complete the work in 6 days?

Show answer & explanation

Correct answer: C

Explanation

The correct answer is option 3 i.e. 8.

Given:

12 men can complete a work in 10 days

Calculations:

Let P man is required to complete the work in 6 days

According to the question;

⇒ 12 × 10 = P × 6

⇒ P = 20 men

Hence, the extra men required to complete the work = 20 - 12 = 8 men